高速公路声屏障施工注意事项
Matters needing attention in construction of highway sound barrier
1、基础和地梁的地下部分,采用挖孔、挖槽灌注法施工。为了尽量减少对公路路基土的扰动。基础和地梁施工时,超挖部分必须用同标号混凝土灌注。浇注桩基础混凝土时,可以采用铁皮套筒保护土壁,以免土粒混入混凝土。
1. The underground part of foundation and ground beam is constructed by digging holes and trench filling. In order to minimize the disturbance to the roadbed soil. In the construction of foundation and ground beam, the over excavation part must be poured with the labelled concrete. When casting the pile foundation concrete, the iron sleeve can be used to protect the soil wall, so as not to mix the soil particles into the concrete.
声屏障的位置、标高均根据本段高速公路声屏障设置地段相关桩号的断面图选定。故在施工前,施工和安装单位必须对声屏障基础的位置和标高做校核测量。路基边坡有拱形骨架段落,基础间距为2m,每个拱内中间位置处设置一个基础,地梁设置在骨架防护预留槽内。
The location and elevation of the noise barrier are selected according to the section number of the relevant pile numbers in the section of the highway noise barrier. Therefore, before construction, the construction and installation units must check and measure the location and elevation of the noise barrier foundation. The roadbed slope has an arch skeleton section, the base spacing is 2m, and a foundation is set in the middle position of each arch, and the ground beam is arranged in the skeleton protection reservation groove.
2、地梁预埋件由声屏障的安装单位加工和预埋,并需在安装单位配合下灌注混凝土,以确保安装质量。
2. The ground beam embedded parts are machined and buried by the installation units of the sound barriers, and the concrete must be perfused under the installation units to ensure the installation quality.
3、声屏障立柱及安装件的防腐工艺采用热镀锌。
3, the sound barrier column and installation of anti-corrosion process using hot dip galvanizing.
4、声屏障安装时,须先对预埋钢板的水泥等杂物进行清理、打磨、除锈、防腐。对预埋螺栓进行全面检查和整修,并上好润滑油。
4. When installing the sound barrier, we must first clean, polish, remove rust and antisepsis for cement and other sundries. Check and repair the embedded bolts, and lubricate the oil well.
5、路基段立柱安装时,由吊车将声屏障H型钢立柱临时吊装到基础之上,调整H型钢立柱的位置、高度、立柱与立柱的间距,立柱安装时,采用铅垂线控制垂直偏差不大于5mm,桥梁段声屏障安装立柱时,利用与埋在防撞墙上的螺杆,用吊车将声屏障H型钢立柱临时吊起,调整型钢立柱的位置、高度、立柱与立柱的间距。立柱安装时,采用铅垂线控制垂直偏差不大于5mm,立柱与防撞墙之间的间隙用镀锌垫片垫至型钢垂直为止。
5. When the subgrade section column is installed, the H type steel column of the sound barrier is temporarily hoisted to the foundation by the crane. The position and height of the H steel column, the height of the column and the distance between the column and the column are adjusted. The vertical deviation of the vertical line is not greater than 5mm when the vertical column is installed. The crane will temporarily suspend the sound barrier H steel column, adjust the position and height of the steel column, and the distance between the column and the column. When the column is installed, plumb line is adopted to control the vertical deviation not more than 5mm. The gap between the column and the anti-collision wall is made up of zinc plated gasket and vertical steel.
如果该路段存在纵坡,钢筋混凝土地梁可采用小台阶的方法保持H型钢立柱垂直,同时调整H型钢立柱的高度。
If there is a longitudinal slope in the section, the reinforced concrete beam can be used to maintain the vertical H steel column and adjust the height of the H steel column. |